Asfinag work – Weinviertler Schnellstraße S 3 must be partially closed

From now until the beginning of July, the Hollabrunn carriageway for bridge repairs in the area of ​​the Obermallebarn junction can only be used in one lane over a length of around 600 meters with a speed reduction to 80 km/h.

On two weekends, the S 3 between Stockerau Nord and Hollabrunn Mitte has to be closed in one direction from Friday (from 8 p.m.) to Monday (from 5 a.m.) for the repair of the Göllersdorf junction and for various construction measures: From May 20 to May 23 May the lane in the direction of Stockerau and from June 10 to 13 the lane in the direction of Hollabrunn. The detour will take place over a large area via the signposted detour routes (L27 – L2165 – B4). Since the closures can be postponed due to the weather, the exact closure times will be announced on site.

Only a trace from July to October

The main construction work in the section between Obermallebarn and Göllersdorf will start at the beginning of July. One lane with a speed reduction to 80 km/h will then be available in both directions for traffic on the S 3 until the work is completed at the end of October. Furthermore, the access road to the Obermallebarn junction in the direction of Hollabrunn and the access road to the Göllersdorf junction in the direction of Stockerau will be closed. The diversion takes place via the nearest junction.

Share:

Facebook
Twitter
LinkedIn

Leave a Reply

Your email address will not be published.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

On Key

Related Posts